About

Who are we?

WESCAN Field Resources provides Field and Site Management and Consultation for electrical installation in the Commercial, Institutional, Industrial and Transmission & Distribution fields on a contractual basis. Our electrical expertise over the last 45 years covers a wide range from ultra-low DC control voltages to 500,000 volts AC Transmission Services. Our experience spans providing high level low voltage electronic security services for Government Agencies to GREEN Technology Tidal Waters Submersed Turbine Generator Metering Stations to Breaker Replacement of 500KV/2000A with new Siemens 500KV/4200A Breakers and controls within a live BROWN FIELD, to Pumping Station Replacement on the TransCanada Pipeline and complete replacement of two 160 KV Substations SIMULTANEOUSLY while managing the Hydro Line Crews as well as many, many more scenarios, many being on Indigenous Lands, such as the site below.

                                                                                                                                     

On ALL sites, our main goals are Safety first, complete Communication with all involved, On-time supply and completion of the project on time and on budget. As safety is a main requirement on our sites, tidiness is mandatory. All contractors and sub-contractors must submit a SAFE WORK PLAN, including housekeeping, to both the PRINCIPAL and WESCAN prior to mobilization onto the site. Upon agreement with the PRINCIPLE, WESCAN may provide the logistics of the project as well.

WE OFFER:

No task is too small or project too large. As a Construction Manager, the PRINCIPAL remains in control, unlike in a LUMP SUM Contract. WESCAN, as representative agent, will carry out the requirements of the PRINCIPAL in contractually agreed upon tasks.

While acting as the AGENT, WESCAN will honor a fiduciary obligation to the PRINCIPAL and endeavor to act transparent and always in the PRINCIPAL’s best interest. Within our standard agreement we will maintain a hands-on relationship with all multi-trade contractors and sub-contractors and suppliers, private or indigenous landowners, regulatory agencies and environmental agencies.

Where the project may impact the community or businesses and can be of particular interest to the Media or Political stakeholders, WESCAN may promote it’s benefits. Although these types of communications usually are thought of as Managing damage control in cases of incident, communication management can also provide good news about the project.

Mobilization

Under our Early Contractor Involvement, WESCAN will set the parameters of site mobilization, materials deliveries and receiving, taking into account the Lead times in procurement of PRINCIPAL supplied equipment and supplies in the schedule provided, warehousing and construction process procedures. With the various trades and subtrades we will chair the startup and weekly progress meetings and attend all daily safety meetings.

  

We will Audit all work as it proceeds, to ensure proper construction methods and quality controls are being applied, handle all engineered drawings, Inspection reports, Requests for Information (RFI), Request for Change (RFC), Request for Payment (RFP), Field Memos (FM), Change Orders Requests (COR), Change Orders (CO), Non-Compliance Orders (NCO), Utilities Interface, Community Relations and Punch lists as well as monitor and investigate all safety issues along the way. Completion or Partial Completion certificates may be offered and presented along with those payments.

Commissioning

We will initiate a Commissioning plan as a part of, or a complimentary document to, the Project Management Plan. Advance planning of the Commissioning process can and does reduce the risks of prolonging the project in its last stage by outlining the roles and responsibilities of each group involved and that they fully understand the commissioning plan. At this point all Operation and Maintenance Manuals  are available, validated accepted as checked and true and accurate.We will assure System Coordination throughout the integration testing by developing and implementing a Safety and Security Certification Plan contingent for emergencies in close coordination Emergency Responders within the area.

Figure 7-2 – Typical Equipment Commissioning List (sample only)

LEED®ITEMHVAC System (and all integral equipment controls):
X1.Pumps (chilled water) if required
X2.Chillers if required
X3.Piping, cleaning, and purging
X4.Chemical treatment
X5.Ductwork
X6.Air handling units
X7.Heating/A.C  (including controls, piping, pumps, compressors) recovery & ventilating units
X8.Split systems
X9.Air terminal units
X120.Testing, adjusting, and balancing work (TAB)
X11.Unit heaters (area, cabinet)
X12.Building automation system (controlled devices, control loops, and system integration)
X13.Fans & ventilation systems including fume and exhaust evacuation systems
X14.Variable frequency drives
X15.Humidifiers

LEED®ITEMMechanical Systems: (As related to facilities and processes including primary control systems)
X16.Building envelope
 17.Overhead roll-up doors and grilles
X18.Boilers
 19.Bus wash and reclamation system
 20.Elevators (freight and passenger)
 21.Bulk fluid storage and distribution systems including but not limited to diesel fuel, fuel oil, motor oil, antifreeze, chassis grease, automatic transmission fluid, gear oil, windshield washer fluid, and waste fluids
 22.Oil/water separator systems
 23.Paint spray booths
 24.Compressed air system
 25.Domestic water system (plumbing, fixtures etc.)
 26.Piping
 27.Monorail systems and traveling cranes
LEED®ITEMElectrical Systems:
X28.Sweep and scheduled lighting controls (i.e. photocells, occupancy sensors)
 29.Fire alarm system
 30.Emergency power system and transfer switch
X31.UPS
 32.Wiring devices
 33.Transient voltage suppression
 34.Secondary unit substations
 35.Enclosed switches and circuit breakers
 36.Enclosed controllers
 37.Panel boards
 38.Dry-type transformers
 39.Grounding
 40.Battery charging system
 41.Level gauging and leak detection systems for bulk fluid systems and tanks
 42.Fuel management system
 43.Bus traffic control system and pedestrian protection system
 44.Data communications system
 45.Integrated telephone and paging systems
 46.Security system
 47.Closed-circuit television (CCTV) system
 48.Time clock system
LEED®ITEMLife Safety Systems:
 49.Emergency lights and signs
 50.Emergency eye wash
 51.Fire protection (including but not limited to fire pump, standpipe, and sprinkler systems)
 52.Gas detection

                                                                                                                                               

CLOSEOUT

We will, along with the PRINCIPAL and applicable trades, lead a Final Walk Through Inspection of the Facility and create a final punch list of incomplete Contractor items, resolve any outstanding claims, assess and document Lessons Learned, develop a plan for Demobilization, obtain Project acceptance from PRINCIPAL Stakeholders and obtain Certificate of Completion.         

Demobilization

WESCAN will remain on site until all waste and unnecessary materials have been removed by the trades and all decommissioning of temporary facilities and equipment have been removed.